Case Studies / MOUNT STREET

Construction of a subterrain house, with extensive excavations, temporary soil retention, reinforced concrete retaining walls, including voltex waterproof tanking. Superstructure included a steel frame with timber clad finish. Velfac large sliding windows and single-ply sarnafill roof with sedum. Installation of turning platform for cars in basement, installation of passenger lift and 18kw solar panel system to roof with air source heat pump and underfloor heating.

Contract: JCT Intermediate Form / Value: £500K / Duration: 14 months / Service: steel frame & Sarnafil roof